
In
this article a few weeks ago, we ascertained with the use of a ruler,
a map, and some basic information about the volume and weight of gravel,
that the current 18.26 hectare site which we are faced with could just about
manage to produce the required 1 million tonnes of gravel.
However, since publishing that article, we've learned
a few interesting things about the mineral extraction process which effectively
reduces the size of the site in question quite considerably.
There are a number of signifigant obstacles within the remaining 18.26 hectare
site that eat into the workable area quite considerably as the engineers
have regulations and working practices that must be adhered to. These obstacles
include...
Power pylons
Roads
Rivers
Proximity of properties
Sewage pipelines
As has been discussed time and time again, the site is quite obviously split
in two by a public road that forms the main access route into and out of
the village. Namely, Paws Lane.
A minimum 10 metre buffer must be maintained between quarry excavations
and roads to prevent subsidance of the road into the hole. In some situations,
depending on the stability of the ground, this buffer can be bigger, but
for the sake of argument, we'll work with a 10 metre buffer for the time
being.
Next,
there's the power pylons to be considered. To move these would be an enormous
task, requiring the re-positioning of pylons along the line for miles in
each direction. Having spoken to engineers at Sibelco and EDF, we have been
informed that pylons would not be re-routed for a site of this size, so
the excavators would have to work around them.
A minumum 15 metre buffer must be maintained between quarry excavaions and
power pylons to maintain the integrity of their collosssal foundations.
Again, this buffer may be larger, but we'll work with a 15 metre buffer
for now.
But that's not the only issue raised by the power pylons. Access must be
maintained to the pylons to allow the electricity company to get to them.
This takes the form of a causeway, usually between 15 and 20 metres wide.
And we also learn that under health and safety working regulations, heavy
working machinery such as that found in quarries, may not be permitted to
work within a 30 metre radius of any high voltage cables to prevent the
risk of accidental discharge through the air.
The cables that span the MIN93 site hang very low and the excavation is
not a particularly deep one, so we can say with some confidence that the
causeway which allows access to the pylons will follow a line directly below
the cables, linking the pylons and preventing machinery from working below
the cables. This will effectively split the site into four separate smaller
sites.
Similar concerns still remain surrounding the sweage pipeline, which we
all know cuts right through the middle of the site. This will have to be
either re-routed or worked around, and the probability is that the latter
option will be chosen. If this decision is taken, it will effectively sterilise
the area of the site between Paws Lane and the sewage pipeline, further
reducing the workable area.
To
the north of the site, we have a river which feeds into the lakes to the
west of the village where fish are bred. Any polution in that river will
have a seriously detrimental effect on the ability of those lakes to sustain
life and their suitability for fish breeding.
The Save Pentney Action Group has commissioned independent tests into the
purity of the water in this river and several points along its route, and
we are now in possession of the ersults of those tests.
To prevent contamination of this river, an impermiable barrier will have
to be put in place. This will take the form of either a clay barrier or
metal interlocking plates. Either way, it will require another 10 metre
buffer to ensure it is effective.
And finally, although the site was modified recently to move the excavation
further away from the main habitable area of the village, it still comes
unacceptably close to a property on the south eastern corner of the site.
It is reasobable to expect that the site will again be modified to draw
the workings away from this property and the space used to erect earthworks
to deflect sound up and away from the village.
All of these modifications result in a greatly reduced site, covering just
over 10 hectares, as llustrated here in the exclusions map.
According to the calculations in this article,
a site of that size simply cannot sustain the expected yield of 1 million
tonnes, so why on earth are they continuing with this application?
Withdraw it now and save everybody a lot of heartache.